Major improvements coming to urban roads across the Snowy Monaro
Published on 08 February 2024
Heavy patching work is set to begin next week on important urban roads across Berridale, Bombala and Cooma.
This work is part of Council’s unprecedented investment into the Snowy Monaro’s road network this financial year, joining the significant program of urban road resealing that got underway in January 2024.
More than a dozen roads across the three towns will see significantly damaged sections of the road surface removed and replaced.
Residents and businesses located on roads scheduled for resealing will receive a letter from Council’s contractor two weeks prior to the commencement of work.
It is critical that businesses and residents on roads scheduled for heavy patching organise alternative parking while work is underway.
Any vehicles remaining on the street during these roadworks will negatively affect the quality of the completed road surface.
This work is part of Council’s ongoing investment into our region’s road network. Snowy Monaro Regional Council is responsible for maintaining 2,647km of roads across the region – the third highest figure for any Council in NSW.
Council invests millions of dollars every year into our region’s roads. This wider schedule of significant improvements are ratepayer funds in action, supported by generous grant funding from the NSW and Australian Governments.
The majority of funds raised through the 2023/24 special rate variation are being directly invested into roads across the region. This substantial commitment will make travel across the Snowy Monaro faster, safer and more economical for all road users.
While this work has been scheduled in advance, delays and other changes can occur. Poor weather is a common cause for these delays, as is urgent maintenance work that can require the temporary redirection of teams and equipment.
Please email council@snowymonaro.nsw.gov.au or call 1300 345 345 for more information, or with any questions or concerns about this program.
February/March 2024 heavy patching schedule:
Start Date
|
Town
|
Street
|
End Date
|
Wednesday 14 February
|
Bombala
|
Wellington Street
|
Thursday 22 February
|
Wednesday 14 February
|
Bombala
|
Joseph Street
|
Thursday 22 February
|
Wednesday 28 February
|
Berridale
|
Boundary Street
|
Monday 4 March
|
Wednesday 28 February
|
Berridale
|
Myack Street
|
Monday 4 March
|
Thursday 22 February
|
Cooma
|
Boundary Street
|
Friday 1 March
|
Thursday 22 February
|
Cooma
|
Commissioner Street
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Soho Street
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Vale Street
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Massie Street
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Baron Street
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Mittagang Road
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Orana Avenue
|
Thursday 25 March
|
Thursday 22 February
|
Cooma
|
Church Road
|
Thursday 25 March
|